STATUS OF WORK AT COURTYARD SITE AS ON 03.03.2023
BLOCK A
FIFTH FLOOR ROOF SLAB:
FIRST PORTION - Centering work completed and Steel work in progress
SECOND PORTION - Centering work completed.
BLOCK B
FIFTH FLOOR:
FIRST PORTION - Column steel work in progress
SECOND PORTION - Column steel work in progress