WORK STATUS AT QUEENS COURTYARD AS ON 10.06.2024
BLOCK A
3rd Floor Masonry work completed. Lintel work in progress.
4th Floor Three Bed Flat area masonry work completed. Lintel work in progres
4th floor Two Bed Flat area Masonry work in progress.
5th Floor Three Bed flat area masonry work completed except lintel work.
5th Floor Two Bed flat area Masonry work in progress.
10th Floor Roof Slab works in progress.
BLOCK-B
5th Floor Two Bed Flats masonry work in progress.
5th Floor Two Bed Flat area curb works in progress.
10th Floor Slab works completed.